A sample integrated master schedule: a new colocation data-center build and 265-customer migration program, from program governance through legacy site decommission and closure.
Available in three formats. The PDF and Excel versions open on any device; the Microsoft Project file preserves the full schedule logic, dependencies, and resourcing.
The full work breakdown structure with dates and durations — best for quick viewing and sharing.
Download PDFAll 558 tasks with start, finish, duration, milestones, % complete and resources — filter and sort your own way.
Download ExcelThe original Microsoft Project source file with full schedule logic and dependencies, for Project users.
Download .mppThe program is organized into 14 integrated workstreams spanning governance, build, deployment, migration, and closure.
| # | Workstream | Start | Finish | Duration | Tasks | Milestones |
|---|---|---|---|---|---|---|
| 01 | Program Management & Governance | 2026-09-01 | 2028-06-22 | 473 days | 32 | 2 |
| 02 | Requirements & Standards Baseline | 2026-09-01 | 2026-10-19 | 35 days | 22 | 1 |
| 03 | Site Sourcing & Selection | 2026-09-08 | 2026-12-07 | 65 days | 11 | 1 |
| 04 | Commercial & Legal | 2026-09-29 | 2027-07-20 | 211 days | 14 | 6 |
| 05 | Network & Connectivity | 2026-10-20 | 2027-04-19 | 130 days | 26 | 5 |
| 06 | Site Build & Facility Readiness | 2026-12-22 | 2027-03-24 | 67 days | 50 | 5 |
| 07 | Site Network Build | 2027-03-16 | 2027-06-21 | 70 days | 22 | 5 |
| 08 | Compute & Network Hardware Deployment | 2026-12-08 | 2027-05-31 | 125 days | 60 | 5 |
| 09 | Security, Compliance & Certification | 2026-10-01 | 2027-08-03 | 219 days | 35 | 5 |
| 10 | Remote Management & Operations Readiness | 2026-09-23 | 2027-07-05 | 204 days | 14 | 5 |
| 11 | Testing, Acceptance & DR Validation | 2026-10-20 | 2027-07-20 | 196 days | 48 | 10 |
| 12 | Customer Migration (265 customers) | 2026-09-29 | 2028-02-09 | 357 days | 148 | 17 |
| 13 | Legacy Colo Decommission & Exit (6 sites) | 2027-11-11 | 2028-03-22 | 95 days | 55 | 7 |
| 14 | Program Closure | 2028-02-03 | 2028-04-05 | 45 days | 5 | 1 |