Sample Project Plan

New Colo Build & Customer Migration Program

A sample integrated master schedule: a new colocation data-center build and 265-customer migration program, from program governance through legacy site decommission and closure.

558Tasks
14Workstreams
75Milestones
17Resources
~21 moDuration
Download

Get a copy of the plan

Available in three formats. The PDF and Excel versions open on any device; the Microsoft Project file preserves the full schedule logic, dependencies, and resourcing.

PDF

Readable PDF

The full work breakdown structure with dates and durations — best for quick viewing and sharing.

Download PDF
~55 KB · opens anywhere
EXCEL

Excel Workbook

All 558 tasks with start, finish, duration, milestones, % complete and resources — filter and sort your own way.

Download Excel
~33 KB · .xlsx
MS PROJECT

Native .mpp File

The original Microsoft Project source file with full schedule logic and dependencies, for Project users.

Download .mpp
~2.3 MB · Microsoft Project
Note: This is an illustrative sample plan provided to demonstrate our program-planning approach. Names, dates, and quantities are representative and not tied to any specific client engagement.
At a Glance

Program workstreams

The program is organized into 14 integrated workstreams spanning governance, build, deployment, migration, and closure.

#WorkstreamStartFinishDurationTasksMilestones
01 Program Management & Governance 2026-09-01 2028-06-22 473 days 32 2
02 Requirements & Standards Baseline 2026-09-01 2026-10-19 35 days 22 1
03 Site Sourcing & Selection 2026-09-08 2026-12-07 65 days 11 1
04 Commercial & Legal 2026-09-29 2027-07-20 211 days 14 6
05 Network & Connectivity 2026-10-20 2027-04-19 130 days 26 5
06 Site Build & Facility Readiness 2026-12-22 2027-03-24 67 days 50 5
07 Site Network Build 2027-03-16 2027-06-21 70 days 22 5
08 Compute & Network Hardware Deployment 2026-12-08 2027-05-31 125 days 60 5
09 Security, Compliance & Certification 2026-10-01 2027-08-03 219 days 35 5
10 Remote Management & Operations Readiness 2026-09-23 2027-07-05 204 days 14 5
11 Testing, Acceptance & DR Validation 2026-10-20 2027-07-20 196 days 48 10
12 Customer Migration (265 customers) 2026-09-29 2028-02-09 357 days 148 17
13 Legacy Colo Decommission & Exit (6 sites) 2027-11-11 2028-03-22 95 days 55 7
14 Program Closure 2028-02-03 2028-04-05 45 days 5 1